The projects page
Open Maintenance, then Projects. Four figures sit at the top: projects Under way, projects that Need attention because they are at risk or delayed, the Portfolio value with what has been paid to date, and what is Payable now with the retention held.
Filter by status or kind of works, or search by title, number, contractor or site. Each card shows progress, the term and how many days are left, plus any overdue milestones, open snags and variations waiting for a decision.
Add a project
- 1Select New project.
- 2Enter the Title and the Project number. The number uses letters, digits and hyphens and is fixed once saved. Add the Contractor if you want to record who is doing the works.
- 3Choose the Kind of works, the Trade, the City and the Site.
- 4Set the Starts and Planned completion dates and the Contract value.
- 5Under Payment terms, set the Advance payment, the Retention and the Warranty in months. You can also link the AMC contract that will maintain the works afterwards.
- 6Build the Milestone plan: add milestones one by one, or select Use the standard HVAC plan and adjust it. Weight is how much each milestone counts towards progress; Payment is the share of the value claimed when it is completed. Payments can add up to 100% at most.
- Select Create project.
Project statuses
Progress claims, retention and the advance
Select Complete on a milestone to certify its claim: its payment share of the contract value, less the retention and the share of the advance it recovers. The Progress claims card lists every claim with its gross, retention, advance recovery and net amount.
Select Mark paid when a claim or the advance is paid. The amount is recorded as it was on that day. Payable now adds up what has been certified and not yet paid, so if a variation is approved after a claim was paid, the difference shows there.
The retention is held until the warranty ends. After handover, select Release on the retention row when you pay it out.
Variations
Select + Raise on the Variations card to record a change to the agreed scope: an Addition or an Omission, its amount and any extra days the works need. A variation is saved as Proposed.
Approve it to add its amount to the contract value and its days to the completion date, or Reject it to leave both as they are. A decided variation stays on record and cannot be edited.
Snag list and handover
Select + Log on the Snag list card to record a defect found on site. Save and log another keeps the location, so you can walk a floor and log several in a row. Select Resolve when a snag is fixed.
Hand over becomes available once every milestone is complete and every snag is resolved. Handing over starts the warranty, and the project page shows when it ends and when the retention is due.
Documents
Add drawings, method statements, test sheets and handover papers on the Documents card. Photos and PDFs up to 15 MB are accepted, up to 20 per project.
Tips for a faster fix
FAQ
It has been completed, so its claim is certified. A completed milestone stays in the plan and keeps its weight and payment share.